Solar PV Inverter Errors – Growatt

Growatt PV inverter displaying a fault code?

Sometimes a problem indicated can be resolved without the need to call anyone out or replace hardware. If not then it might give a clue as to what the root cause could be.

  • Check to see if your fault code is in the list below.
  • All fault codes shown are manufacturer supplied.
  • Follow any manufacturers advice indicated next to your error code.
  • Many inverters will show an error indicating an internal failure, this usually means a replacement is required, call us for advice or a quote.
  • If your inverter does not have a screen and is off-line you could try our home troubleshooting guide to try to get your solution working again.
  • If all else fails we would be happy to take your call on 0330 345 3400
Commercial inverter fitting service
maintenance-1
Domestic inverter fitting service without cloud connection

Repairs & Maintenance

Additional Services

Error Code

Description

Solution

No AC connection

No utility grid connected or utility grid power failure

This error would normally occur during a grid failure, if you still have electricity connected to your property then check your AC isolator or circuit breaker. If both the isolator and CB are ‘on’ and the problem persists submit a maintenance service request.

AC V outrange

Utility grid voltage is out of permissible range

This could happen particularly in the summer months if there is a lot of solar in your area, if the problem persists please submit a maintenance service request.

AC F outrange

Utility grid frequency is out of range

This could happen particularly in the summer months if there is a lot of solar in your area, if the problem persists please submit a maintenance service request.

Over temperature

Temperature out of range

Restart inverter. If still present, contact Growatt. NOTE: Ensure inverter is not covered causing the inverter to overheat

PV isolation low

Insulation problem

This can indicate a earth fault on the roof. Submit a maintenance service request

Output high DCI

Output current DC offset too high

Restart the inverter. If the problem still persists submit a maintenance service request.

Residual 1 high

Leakage current too high

Restart the inverter. If the problem still persists submit a maintenance service request.

PV voltage high

DC input voltage is exceeding the maximum tolerable value

Disconnect DC switch immediately and switch off system. Submit a maintenance service request.

Auto test failed

Auto test failed

Restart the inverter and fault will clear.

100

Voltage fault

Submit a maintenance service request.

101

Communication fault

Turn off the DC switch and make the inverter totally shut down. Turn on the DC switch to see if the error still exists. If the error persists submit a maintenance service request.

102

Consistent fault. Data received by master and slave processor are different

Turn off the DC switch and make the inverter totally shut down. Turn on the DC switch to see if the error still exists. If the error persists submit a maintenance service request.

116

EEPROM Fault

When the inverter displays Error: 116, it means there is failure in reading or writing EEPROM.
1. Check when the error appears: if in the morning, if only in the morning, contact Growatt for support.
2. If the error appears all day; (a) restart the inverter, check if the error still exists. (b) If the fault is sustained, the control board needs to be replaced. Submit a maintenance service request.

117

Relay fault

There is something wrong with the relay circuit. Restart the inverter, if the problem still persists submit a maintenance service request.

118

Init model fault

Submit a maintenance service request.

119

GCFI device damage

Something may be wrong with the GCFI device inside the inverter.
(a) Restart the invert for 2-3 times, check whether the error still exists.
(b) If the error still exists submit a maintenance service request.

120

HCT Fault

When the inverter shows Error 120 it means something is wrong with the current sensor. Restart the inverter and if the error persists submit a maintenance service request.

121

Communication fault, master processor can’t receive data from slave processor

See error 101 and 102.

122

Bus voltage fault

Submit a maintenance service request.

Remember, our engineering staff are never more than an hour away and can have you back up and running in no time

Give us a call, we will take your details, arrange an engineer, and aim to resolve your solar problem as soon as possible.

Photos are always an effective way to show us your problem too.

 

Call Bolido Solar on 0330 345 3400 or use the inquiry form and we will call you back

Tim Foreman
Tim Foreman
4 weeks ago
Read More
Scott designed and carried out a PV cell installation recently. The quote was competitive and the correspondence quick and concise. The fitting was arranged within a week, once the specification was agreed. On site, assisted by Mike, they were helpful and friendly and despite a difficult routing for the cable they came up with a successful solution. The end result is a very tidy, externally & internally, solar fit for the property. Great job and communication throughout, overall I'm very satisfied with their service and would recommend them.
Elspeth Robinson
Elspeth Robinson
3 weeks ago
Read More
Thank you for your outstanding service we received with regards to our solar panels which needed a new inverter. In next to no time, the problem was identified, a replacement ordered, delivered and fitted and the solar panels immediately started to record our readings. I have 100% confidence in recommending Bolido!
Greg Bertrum
Greg Bertrum
2 weeks ago
Read More
Very refreshing to get such a thorough and decent service. My company, a solar installations company needed technical assistance on-site for two projects. We also needed help with some of our own IT systems particularly with providing secure internet and network access between us and our clients, primarily for sharing power generation data but also increasingly alongside power usage data. Scott and his team were great with our clients and we just left to it. They were also quick to understand exactly what we wanted to achieve. They carried out all of the work, quickly, cleanly and with the minimum of fuss. We are now in a great position network and IT wise, moving forward we are confident in being able to service bigger clients with however sophisticated a network solution they might require. Highly recommend this company.
Little Miss Psycho
Little Miss Psycho
1 week ago
Read More
Fantastic and thorough service from these guys following birds nesting and ruining the connections on our solar installation. Great communications throughout, and friendly professional service.